FEBRUARY 2025 Update
- Continue underground piping installation at the main entrance of the south parking lot.
- Punchlist for auditorium.
- In Area C pour concrete slab, finish steel and deck detailing, and start framing exterior walls.
- Complete CMU wall construction in gym area, start swinging steel and deck, and apply air barrier to CMU walls.
- Finish above ceiling rough-ins in locker room.