JUNE 2025 Update

  • Area A – Complete hoist installation and stage curtains.
  • Area C – Complete walls and parapet framing, roofing, fireproofing, and dry system piping. Continue framing, MEP, pipe grid in TV studio room, and acoustical spray in dining/media areas.
  • Area E – Continue ductwork, plumbing, light fixtures, painting, wall panel installation, gym equipment, ceiling grid, and fiber cement siding.
  • Remove and replace windows in LG testing room and build temporary walls near the auxiliary gym.

MAY 2025 Update

  • Continue sanitary and storm-line install in East side and continue grading.
  • Area C – Complete roofing and continue fireproofing, framing interior walls, and installation of all MEP utilities.
  • Complete roofing, fireproofing, and painting in gym and athletic storage areas.
  • Install basketball hoops in gym and deliver wood flooring.
  • Complete installation of lockers, toilet partitions, and toilet accessories.

APRIL 2025 Update

  • Sitework – Continue sanitary and storm-line install and continue grading.
  • Area A – Install hoist system at auditorium.
  • Area C – Continue roofing, fireproofing, framing exterior and interior walls, and installation of MEP utilities.
  • Area E – Complete roofing, fireproofing, and ductwork and electrical conduits in the gym.
  • Begin painting in gym and athletic storage areas and installation of lockers, toilet partitions, and accessories.

MARCH 2025 Update

  • Continue underground piping installation at South parking lot main entrance.
  • Area A – Continue working on punchlist.
  • Area C – Steel and deck detailing, framing exterior walls and parapets, roofing, fireproofing, CMU/masonry shear walls.
  • Site concrete/asphalt work.
  • Area E – Steel and deck detailing, air barrier for CMU walls, brick façade, roofing, resinous flooring in locker rooms.

FEBRUARY 2025 Update

  • Continue underground piping installation at the main entrance of the south parking lot.
  • Punchlist for auditorium.
  • In Area C pour concrete slab, finish steel and deck detailing, and start framing exterior walls.
  • Complete CMU wall construction in gym area, start swinging steel and deck, and apply air barrier to CMU walls.
  • Finish above ceiling rough-ins in locker room.

JANUARY 2025 Update

  • Continue underground piping installation at the main entrance of the South parking lot.
  • Complete all necessary work in the auditorium wing for turnover.
  • Begin installing lockers in the locker rooms and complete CMU wall construction in the gym area.
  • In Area C, finish under-slab rough-ins, pour concrete slab, and begin swinging steel.

December 2024 Update

  • Continue installing lights, speakers, and wood wall paneling in auditorium.
  • Begin installing telescoping stands, folding panel partition, and fixed seating in auditorium.
  • Continue prep for under slab rough-ins and start pouring concrete slab in Area C.
  • Continue installation of ductwork, wiring, and sprinkler above ceiling in locker rooms.
  • Continue CMU wall installation in gym and athletic storage area.
  • Begin installing ceramic tiling in locker rooms and framing at exterior canopy at health room.
  • Continue underground utilities installation at south parking lot.

NOVEMBER 2024 Update

  • Continue pouring foundations in Area C and prep for under slab rough-ins.
  • Grade and install underground utilities.
  • Continue installation of ductwork, wiring, and sprinkler in locker rooms.
  • Install CMU wall in gym and athletic storage area.
  • Install lights, speakers, and wood wall paneling in auditorium.
  • Install telescoping stands in house areas.
  • Install flooring, railing, and painting in auditorium wing.

October 2024 Update

  • Grade building pad and pour foundations in Area-E.
  • Grade building pad in Area-C.
  • Fireproofing in locker rooms.
  • Install base pave at North West section of South parking lot.
  • Continue interior work inside the auditorium.
  • Grade pad and prep for foundations in West courtyard.

SEPTEMBER 2024 Update

  • Completion of Phase 2 demolition.
  • Pouring new foundations in Area C courtyards.
  • Installing hangers in locker rooms ahead of fireproofing.
  • Sitework continues in south parking lot.