NOVEMBER 2025 Update
- Sitework – Continue grading in East parking lot, laying sod in front of concession stand area, pouring curb/gutter and sidewalk, removing existing pavement, and builtup of bio-ponds.
- Area A – Complete working on ELTP panel.
- Occupied Space – Completing punchlist items.