Sitework – Continue sidewalk and curb installation and built-up of basketball court. Mill and run utilities in parking lot and grade loading dock area.
Area A – Install emergency electrical panel in auditorium.
Area C – Continue installing drywall, finishing, windows, and storefront. Begin installing kitchen equipment, ceiling grid, and utilities above ceiling. Complete resinous flooring in kitchen, concession stands, and greenhouse, and finish staining brick in courtyard. Paint ceiling and install lighting in media center and dining area.
Area E – Complete work inside the gym and work on punchlist items.