December 2023 Update

  • Continuing VCT, painting, ceiling grid and drywall.
  • Setting rooftop equipment.
  • Addition roof is complete and re-roofing the existing roof areas.
  • Installing wall panels.
  • Completing new parking lot.

November 2023 Update

  • Casework is starting.
  • Interior glazing and storefront work.
  • Light fixtures.
  • Plumbing fixtures.
  • Interior finishes.

October 2023 Update

  • VCT flooring is starting.
  • Ceramic tile is starting.
  • Interior painting continues.
  • Site concrete/asphalt work.
  • Elevator installation is starting.

September 2023 Update

  • Interior drywall, paint, and MEP rough-ins are progressing.
  • Roof is nearing completion.
  • Installing exterior façade panels.
  • Site work for the new bus loop will begin in a few weeks.