Author name: KimD

AUGUST 2024 Update

  • Building demolition.
  • Completion of underground stormwater management system.
  • Curb and gutter and asphalt paving south parking lot.
  • Begin installing foundations.
  • MEP rough-ins in locker rooms.

july 2024 Update

  • Building demolition and abatement.
  • Installation of underground stormwater management system under parking lot.

June 2024 Update

  • Selective interior demolition.
  • Underground plumbing in locker rooms.
  • Cut/Cut/Make Safe MEPs for upcoming abatement/ demolition of building.
  • Excavating for UGS-1 structure in south parking lot.
  • Hanging drywall at room east of auditorium.

may 2024 Update

  • Demolition of ceilings throughout Phase 2 area.
  • Sediment and erosion controls.
  • Preparing for installation of the underground stormwater facility.

april 2024 Update

  • Turnover of Phase 1 to students and staff.
  • Mechanical systems – final testing and balancing.
  • Landscaping.
  • Punchlist Phase 1 areas.
  • Phase 2 sediment controls/site preparation.
  • Soft demolition in locker rooms.

MARCH 2024 Update

  • Final finishes.
  • Site concrete.
  • Paving and striping.
  • Landscaping and sod.
  • Start up of MEPS systems and commissioning.
  • Final inspections and cleaning.

february 2024 Update

  • Flooring continues.
  • Fixtures and trims continue.
  • Finish cleaning.
  • Equipment start-ups/testing.

january 2024 Update

  • Flooring – VCT, ceramic tile, and carpet tile.
  • Casework.
  • Acoustical ceiling tile.
  • Marker boards and bulletin boards.
  • Fixtures and trim.
  • Site concrete.