AUGUST 2024 Update
- Building demolition.
- Completion of underground stormwater management system.
- Curb and gutter and asphalt paving south parking lot.
- Begin installing foundations.
- MEP rough-ins in locker rooms.
july 2024 Update
- Building demolition and abatement.
- Installation of underground stormwater management system under parking lot.
June 2024 Update
- Selective interior demolition.
- Underground plumbing in locker rooms.
- Cut/Cut/Make Safe MEPs for upcoming abatement/ demolition of building.
- Excavating for UGS-1 structure in south parking lot.
- Hanging drywall at room east of auditorium.
may 2024 Update
- Demolition of ceilings throughout Phase 2 area.
- Sediment and erosion controls.
- Preparing for installation of the underground stormwater facility.
april 2024 Update
- Turnover of Phase 1 to students and staff.
- Mechanical systems – final testing and balancing.
- Landscaping.
- Punchlist Phase 1 areas.
- Phase 2 sediment controls/site preparation.
- Soft demolition in locker rooms.
MARCH 2024 Update
- Final finishes.
- Site concrete.
- Paving and striping.
- Landscaping and sod.
- Start up of MEPS systems and commissioning.
- Final inspections and cleaning.
february 2024 Update
- Flooring continues.
- Fixtures and trims continue.
- Finish cleaning.
- Equipment start-ups/testing.
january 2024 Update
- Flooring – VCT, ceramic tile, and carpet tile.
- Casework.
- Acoustical ceiling tile.
- Marker boards and bulletin boards.
- Fixtures and trim.
- Site concrete.