December 2024 Update
- Continue installing lights, speakers, and wood wall paneling in auditorium.
- Begin installing telescoping stands, folding panel partition, and fixed seating in auditorium.
- Continue prep for under slab rough-ins and start pouring concrete slab in Area C.
- Continue installation of ductwork, wiring, and sprinkler above ceiling in locker rooms.
- Continue CMU wall installation in gym and athletic storage area.
- Begin installing ceramic tiling in locker rooms and framing at exterior canopy at health room.
- Continue underground utilities installation at south parking lot.