MAY 2025 Update

  • Continue sanitary and storm-line install in East side and continue grading.
  • Area C – Complete roofing and continue fireproofing, framing interior walls, and installation of all MEP utilities.
  • Complete roofing, fireproofing, and painting in gym and athletic storage areas.
  • Install basketball hoops in gym and deliver wood flooring.
  • Complete installation of lockers, toilet partitions, and toilet accessories.