NOVEMBER 2024 Update

  • Continue pouring foundations in Area C and prep for under slab rough-ins.
  • Grade and install underground utilities.
  • Continue installation of ductwork, wiring, and sprinkler in locker rooms.
  • Install CMU wall in gym and athletic storage area.
  • Install lights, speakers, and wood wall paneling in auditorium.
  • Install telescoping stands in house areas.
  • Install flooring, railing, and painting in auditorium wing.