December 2024 Update

  • Continue installing lights, speakers, and wood wall paneling in auditorium.
  • Begin installing telescoping stands, folding panel partition, and fixed seating in auditorium.
  • Continue prep for under slab rough-ins and start pouring concrete slab in Area C.
  • Continue installation of ductwork, wiring, and sprinkler above ceiling in locker rooms.
  • Continue CMU wall installation in gym and athletic storage area.
  • Begin installing ceramic tiling in locker rooms and framing at exterior canopy at health room.
  • Continue underground utilities installation at south parking lot.

NOVEMBER 2024 Update

  • Continue pouring foundations in Area C and prep for under slab rough-ins.
  • Grade and install underground utilities.
  • Continue installation of ductwork, wiring, and sprinkler in locker rooms.
  • Install CMU wall in gym and athletic storage area.
  • Install lights, speakers, and wood wall paneling in auditorium.
  • Install telescoping stands in house areas.
  • Install flooring, railing, and painting in auditorium wing.

October 2024 Update

  • Grade building pad and pour foundations in Area-E.
  • Grade building pad in Area-C.
  • Fireproofing in locker rooms.
  • Install base pave at North West section of South parking lot.
  • Continue interior work inside the auditorium.
  • Grade pad and prep for foundations in West courtyard.

SEPTEMBER 2024 Update

  • Completion of Phase 2 demolition.
  • Pouring new foundations in Area C courtyards.
  • Installing hangers in locker rooms ahead of fireproofing.
  • Sitework continues in south parking lot.

AUGUST 2024 Update

  • Building demolition.
  • Completion of underground stormwater management system.
  • Curb and gutter and asphalt paving south parking lot.
  • Begin installing foundations.
  • MEP rough-ins in locker rooms.

july 2024 Update

  • Building demolition and abatement.
  • Installation of underground stormwater management system under parking lot.

June 2024 Update

  • Selective interior demolition.
  • Underground plumbing in locker rooms.
  • Cut/Cut/Make Safe MEPs for upcoming abatement/ demolition of building.
  • Excavating for UGS-1 structure in south parking lot.
  • Hanging drywall at room east of auditorium.

may 2024 Update

  • Demolition of ceilings throughout Phase 2 area.
  • Sediment and erosion controls.
  • Preparing for installation of the underground stormwater facility.

april 2024 Update

  • Turnover of Phase 1 to students and staff.
  • Mechanical systems – final testing and balancing.
  • Landscaping.
  • Punchlist Phase 1 areas.
  • Phase 2 sediment controls/site preparation.
  • Soft demolition in locker rooms.

MARCH 2024 Update

  • Final finishes.
  • Site concrete.
  • Paving and striping.
  • Landscaping and sod.
  • Start up of MEPS systems and commissioning.
  • Final inspections and cleaning.