December 2024 Update
- Continue installing lights, speakers, and wood wall paneling in auditorium.
- Begin installing telescoping stands, folding panel partition, and fixed seating in auditorium.
- Continue prep for under slab rough-ins and start pouring concrete slab in Area C.
- Continue installation of ductwork, wiring, and sprinkler above ceiling in locker rooms.
- Continue CMU wall installation in gym and athletic storage area.
- Begin installing ceramic tiling in locker rooms and framing at exterior canopy at health room.
- Continue underground utilities installation at south parking lot.
NOVEMBER 2024 Update
- Continue pouring foundations in Area C and prep for under slab rough-ins.
- Grade and install underground utilities.
- Continue installation of ductwork, wiring, and sprinkler in locker rooms.
- Install CMU wall in gym and athletic storage area.
- Install lights, speakers, and wood wall paneling in auditorium.
- Install telescoping stands in house areas.
- Install flooring, railing, and painting in auditorium wing.
October 2024 Update
- Grade building pad and pour foundations in Area-E.
- Grade building pad in Area-C.
- Fireproofing in locker rooms.
- Install base pave at North West section of South parking lot.
- Continue interior work inside the auditorium.
- Grade pad and prep for foundations in West courtyard.
SEPTEMBER 2024 Update
- Completion of Phase 2 demolition.
- Pouring new foundations in Area C courtyards.
- Installing hangers in locker rooms ahead of fireproofing.
- Sitework continues in south parking lot.
AUGUST 2024 Update
- Building demolition.
- Completion of underground stormwater management system.
- Curb and gutter and asphalt paving south parking lot.
- Begin installing foundations.
- MEP rough-ins in locker rooms.
july 2024 Update
- Building demolition and abatement.
- Installation of underground stormwater management system under parking lot.
June 2024 Update
- Selective interior demolition.
- Underground plumbing in locker rooms.
- Cut/Cut/Make Safe MEPs for upcoming abatement/ demolition of building.
- Excavating for UGS-1 structure in south parking lot.
- Hanging drywall at room east of auditorium.
may 2024 Update
- Demolition of ceilings throughout Phase 2 area.
- Sediment and erosion controls.
- Preparing for installation of the underground stormwater facility.
april 2024 Update
- Turnover of Phase 1 to students and staff.
- Mechanical systems – final testing and balancing.
- Landscaping.
- Punchlist Phase 1 areas.
- Phase 2 sediment controls/site preparation.
- Soft demolition in locker rooms.
MARCH 2024 Update
- Final finishes.
- Site concrete.
- Paving and striping.
- Landscaping and sod.
- Start up of MEPS systems and commissioning.
- Final inspections and cleaning.