JUNE 2025 Update

  • Area A – Complete hoist installation and stage curtains.
  • Area C – Complete walls and parapet framing, roofing, fireproofing, and dry system piping. Continue framing, MEP, pipe grid in TV studio room, and acoustical spray in dining/media areas.
  • Area E – Continue ductwork, plumbing, light fixtures, painting, wall panel installation, gym equipment, ceiling grid, and fiber cement siding.
  • Remove and replace windows in LG testing room and build temporary walls near the auxiliary gym.