JULY 2025 Update
- Sitework – Mill and overlay, sidewalk and curb installation, built-up of basketball court area.
- Area A – Complete auditorium lighting.
- Area C – Continue drywall and finishing, built-up of courtyard area, and installation of kitchen equipment, windows and storefront, ceiling grid, and utilities above ceiling.
- Area E – Complete all scope work.